Every homeowner in Greater Boston asks the same question before signing a contract: "How long will my kitchen take?" And almost every answer they've gotten online is wrong — or at least misleading. The truth is that a kitchen remodel timeline isn't driven by how fast your contractor can swing a hammer. It's driven by cabinets. Specifically, the 8–15 week lead time for semi-custom and custom cabinetry that sits at the center of your entire schedule.
We're Schlickmann Construction, a licensed general contractor (MA CSL-121587) working across Stoneham, Winchester, Lexington, Newton, Cambridge, and the surrounding towns. We've run enough kitchens to tell you exactly where the weeks go — and how to sequence the work so you're not sitting in a gutted kitchen for two extra months waiting on a delivery truck. This is the honest version.
The Real Kitchen Remodel Timeline: 8 to 16 Weeks Total
A full kitchen remodel in Greater Boston typically runs 8 to 16 weeks from contract signing to final walkthrough. But here's the part most people miss: only about 4 to 6 of those weeks are actual on-site construction. The rest is lead time, design finalization, and permitting — work that happens before a single cabinet gets torn out.
Here's the general breakdown for a standard kitchen (12x14, mid-range finishes, no structural changes):
- Weeks 1–2: Design finalization, measurements, material selection, cabinet order placed
- Weeks 2–4: Permit application and approval through your town's building department
- Weeks 3–14: Cabinet fabrication and delivery (the bottleneck — runs in parallel with early construction)
- Weeks 4–6: Demolition, rough plumbing, rough electrical, inspections
- Weeks 6–8: Drywall, paint, flooring
- Weeks 9–12: Cabinet installation, countertop templating and install
- Weeks 12–14: Backsplash, appliance hookup, plumbing trim, final electrical, punch list
Notice how cabinets are ordered in week 1 or 2, not week 6. That's not an accident — that's the whole game. If your contractor waits until demolition is done to order cabinets, you've just added 8–15 weeks of dead time to your project. We order the moment the design is locked.
Why Custom Cabinets Drive the Whole Schedule
Cabinets are the single longest-lead item in a kitchen. Everything else — countertops, tile, appliances, fixtures — can be sourced in days or a couple of weeks. Cabinets can't, and here's why.
Stock vs. Semi-Custom vs. Custom Lead Times
The cabinet category you choose has a bigger impact on your kitchen remodel timeline than almost any other decision:
- Stock cabinets: 1–3 weeks. Big-box or in-stock lines in standard sizes. Limited finishes and configurations, but fast.
- Semi-custom cabinets: 6–10 weeks. This is what most Greater Boston kitchens use — real wood, dozens of door styles, modified sizes. The sweet spot of quality and cost.
- Custom cabinets: 10–15 weeks, sometimes longer. Built to your exact dimensions in a shop, any finish, any configuration. Necessary for older Winchester and Newton homes with non-standard wall runs and out-of-square rooms.
In older homes across Medford, Arlington, and Cambridge — where walls are rarely plumb and ceiling heights vary — semi-custom or full custom is often the only way to get a clean, gapless install. That quality comes with the 8–15 week wait. There's no way around it, and any contractor promising a full custom kitchen in six weeks is either using stock boxes or lying to you.
Why Ordering Late Kills Your Schedule
The most common mistake we see from homeowners who tried to self-manage or hired the wrong contractor: cabinets weren't ordered until demolition was complete. The logic seems reasonable — "let's measure the empty room first." But it's a disaster. Now you've got a gutted, unusable kitchen and you're staring down 10 more weeks of lead time before anything gets installed.
The right sequence is to finalize the design, take precise measurements, and place the cabinet order before demolition even begins. Then demolition, rough-ins, and inspections happen during the fabrication window. By the time cabinets arrive, the room is drywalled, painted, and floor-ready. That parallel sequencing is the difference between a 10-week kitchen and a 20-week one.
Permits and Inspections in Greater Boston
Every kitchen remodel that touches plumbing, electrical, or gas requires permits — and in Massachusetts, that's virtually every kitchen. Under the Massachusetts State Building Code (780 CMR), and the electrical requirements of 527 CMR 12.00 (Massachusetts Electrical Code, based on NEC), you'll typically need a building permit plus separate electrical, plumbing, and gas permits.
A few code specifics that regularly affect kitchen timelines:
- GFCI protection is required for all kitchen countertop receptacles, and your counter must have receptacles spaced so no point along the wall is more than 24 inches from an outlet.
- Dedicated 20-amp circuits are required for small-appliance loads — a common reason older Somerville and Belmont kitchens need panel work that adds days to the schedule.
- Inspection scheduling varies by town. Stoneham and Woburn typically turn inspections around in 1–3 business days; larger cities like Cambridge and Newton can take longer during busy seasons.
Permit approval itself usually takes 1–3 weeks depending on the municipality. In Lexington and Brookline, plan reviews for larger projects can run on the longer end. Because we pull permits under our own license (CSL-121587) rather than asking homeowners to do it, we start this process the same week the contract is signed — so it overlaps with cabinet lead time instead of stacking on top of it. For the full scope of what we handle, see our kitchen remodeling services.
How to Sequence the Work So Nothing Sits Idle
A tight kitchen remodel timeline is all about overlap. The goal is to keep the long-lead items (cabinets, countertops) moving in the background while on-site work progresses in the foreground. Here's how a well-run project sequences:
Phase 1: Pre-Construction (Weeks 1–3)
- Lock the design and layout — no changes after this point without schedule impact
- Take final field measurements and place the cabinet order immediately
- Submit permit applications
- Order countertops' slab selection and appliances (verify appliance lead times — some panel-ready and pro ranges run 8+ weeks themselves)
Phase 2: On-Site Construction (Weeks 4–8)
- Demolition (2–4 days)
- Rough plumbing and electrical (1 week), then rough inspections
- Insulation and drywall (1 week)
- Priming, painting, and flooring installation
All of this happens while cabinets are still being built. This is the entire reason a professionally managed kitchen finishes weeks faster than a piecemeal one.
Phase 3: Finish and Punch (Weeks 9–14)
- Cabinet installation (2–4 days for a standard kitchen)
- Countertop templating — this happens after cabinets are set, then 1–2 weeks for fabrication and install
- Backsplash tile
- Plumbing and electrical trim-out, appliance hookup, final inspections, punch list
One scheduling trap worth flagging: countertops can't be templated until cabinets are physically installed. That means there's an unavoidable 1–2 week gap between cabinet install and countertop install where you'll have base cabinets but no working counters. Plan your temporary kitchen setup around it.
What Adds Time to a Kitchen Remodel
The 8–16 week range assumes a relatively straightforward project. These factors push it longer:
- Moving walls or plumbing: Relocating a sink or removing a load-bearing wall adds structural work, engineering, and additional inspections — often 2–4 weeks.
- Knob-and-tube or outdated wiring: Common in pre-1950 Watertown, Arlington, and Somerville homes. Full rewiring adds time and cost.
- Custom range hoods and specialty appliances: These have their own 8–12 week lead times that can eclipse even the cabinets.
- Mid-project design changes: Swapping cabinet colors or layout after fabrication starts can reset your clock entirely.
- Larger scope creep: Many kitchen projects expand into adjacent spaces. If that's your direction, our full home renovation services let us sequence multiple rooms so trades aren't doubling back.
Frequently Asked Questions
How long does a kitchen remodel take in Greater Boston?
A standard kitchen remodel runs 8 to 16 weeks from contract to completion. Only about 4–6 weeks of that is on-site work; the rest is cabinet lead time (8–15 weeks for semi-custom or custom) and permitting (1–3 weeks). Structural changes, wiring upgrades in older homes, and specialty appliances can extend the timeline.
Can I speed up my kitchen remodel timeline?
Yes — the biggest lever is ordering cabinets the moment your design is finalized, not after demolition. Choosing semi-custom or stock cabinets over full custom can shave weeks. Locking your design early and avoiding mid-project changes keeps the schedule tight. The single fastest path is hiring a contractor who overlaps permitting and construction with the cabinet lead time.
Do I need a permit for a kitchen remodel in Massachusetts?
Almost always. Under the Massachusetts State Building Code (780 CMR), any project involving plumbing, electrical, or gas work requires permits — separate building, electrical, plumbing, and gas permits are typical. Even a straightforward cabinet-and-counter refresh usually triggers electrical work for GFCI and dedicated circuits. We pull all permits under our license so you don't have to.
Get a Realistic Timeline From a Contractor Who's Done It
The difference between a kitchen that finishes in 10 weeks and one that drags to 20 comes down to sequencing — and sequencing starts with ordering cabinets before you swing the first hammer. At Schlickmann Construction (MA license CSL-121587), we self-perform every phase with no subcontractors, which means one crew, one schedule, and no finger-pointing when trades collide. We're BBB A+ rated with a 5.0★ Google review record across Stoneham, Winchester, Lexington, Newton, Cambridge, and the surrounding Greater Boston towns. If you want a straight answer on your kitchen remodel timeline — with real cabinet lead times, real permit windows, and a schedule you can plan around — contact us for a free estimate and we'll map out your project week by week.